400/132/20 kV Shahmanar 2 as part of the project "400/132/20 kV of Shahmaran 2 and Bam substations and 400 kV transmission line of Shahmaran 2 substation" was energized on March 2019.
The valuable results of this project are as follow; power transmission network stability, voltage levels improvement and improvement of power quality in Kerman Regional Electric Company network as well as the entire network. Therefore, this substation plays a key role in the region due to industrial and urban consumption increasing and the need to provide reliable electricity to supply energy to factories also to provide welfare for people living in the urban and rural areas in the southwest of Kerman Province and northern Hormozgan province.
In this project, Monenco Iran was responsible to render consultancy, engineering and supervision services in which by using the modern engineering tools and national and international standards also relying on its qualified experts was able to carry out the project with the highest quality.